Technology

Bosshard-Farben AG - New production facility and site restructuring

Originally, Bosshard-Farben AG planned to expand logistics only. However, a thorough process analysis by IE Technology showed that investing in a modern production facility at the Rümlang headquarters would be the more strategic choice. As general planner, IE Technology delivered a new building that efficiently brings together production, laboratory and logistics.

Strategic realignment through process analysis

Project

Feasibility and concept studies; master plan, tendering and execution for the site restructuring – including construction of a new production facility

Client

Bosshard-Farben AG

Key Data

Planning and Execution
IE Technology
Construction Period
24 months
Usable area - new building production
4,450 m²
Investment Volume excluding Equipment
CHF 16.8 million

Working Together for Project Success

Services provided by IE Group

  • Construction of a future-ready production facility with 4,450 m² of usable area in Rümlang
  • Implementation in two phases while operations continued – without interrupting production
  • Gravity-fed production flow across four floors – raw materials at the top, dispatch at the bottom
  • Holistic hygiene concept for the biocide room, including airlocks, eyewash station and emergency shower
  • Investment volume CHF 16.8 million – delivered as general contractor
“We originally intended to expand our logistics capacity. Instead, IE Technology convinced us – based on strategically sound process analyses – to invest in production. The new building is a complete success. I can recommend IE’s factory-planning team without reservation.”
Philipp Bosshard
Philipp Bosshard
Managing Director Bosshard-Farben AG

Challenges & Solutions

Capacity expansion without the planned neighboring plot

IE Technology prepared several feasibility and concept studies and developed a tailored master plan to restructure the existing site. By intelligently rearranging all functional areas, space and capacity were created for a new production facility – at significantly lower cost than the originally planned new build on the neighbouring property.

Hygiene concept for safe biocide processing

Drawing on extensive industry know-how from the food and pharmaceutical sectors, IE Technology developed and implemented a sophisticated hygiene concept for the biocide room. Employee protection and full compliance with legal requirements were ensured. The new facility is considered one of the most modern paint factories in Europe.

Relocating large-scale equipment while operations continued

IE Technology coordinated the relocation of the large tanks and the container washing system, leveraging its industrial construction experience. All measures were completed smoothly and without disrupting ongoing operations. The result: Bosshard increased flexibility and capacity across logistics and, at the same time, expanded production capacity – just in time for the company’s 75th anniversary.

The Project in Detail

Just in time for the 75th anniversary of Bosshard-Farben AG in Rümlang, IE Technology completed the full restructuring of the production site and handed over one of Europe’s most modern paint factories. As part of several feasibility studies and master plans, IE’s experts demonstrated that Bosshard’s original decision to expand the site would have exceeded the available budget. Instead, they developed a tailored concept to restructure the existing premises, enabling the same increase in logistics capacity at significantly lower cost. This included a new factory building, which also made it possible to increase production capacity and broaden the product range.

The Challenge

For more than 75 years, Bosshard-Farben AG has been producing a wide range of paints in Rümlang. When the site’s logistics reached its capacity limits in 2017 due to the growing product variety, management intended to expand the site. The plan was to relocate all logistics to a new building on an adjacent plot. However, a feasibility study by IE Technology showed that a new build on the neighbouring property that had already been purchased would exceed the target budget. Yet the need to expand capacity remained. IE’s experts therefore faced the challenge of developing an alternative solution – without the additional plot and within the defined budget.

Key Success Factors

IE prepared several feasibility and concept studies and ultimately developed a tailored master plan for the most efficient capacity expansion. Instead of outsourcing logistics, the entire site was restructured to create space for a new production facility and to noticeably optimise all other processes.

During execution, IE Technology was able to demonstrate its full industrial construction expertise. The relocation of the huge binder tanks and the container washing system, as well as the highly complex hygiene concept for safe biocide processing, were implemented with distinction – supported by industry know-how from the food and pharmaceutical sectors. The result: Bosshard increased the flexibility and capacity of its entire logistics operation very efficiently, stayed within the desired budget and, at the same time, achieved an increase in production capacity with one of Europe’s most modern paint factories.

Download

Deepen Your Knowledge

Deepen your knowledge

Discover further details in our Project Insight.

Let's lay the foundation for your project

Every successful journey starts with a clear direction. Let’s align on your goals and establish the strategic basis for a successful project.