Mikron Switzerland AG - Capacity Expansion for Automation Systems

Mikron Automation reached its capacity limits in Boudry. As general planner, IE Technology planned and executed an extension and a new energy centre to sustainably secure assembly capacity for highly complex automation systems.

Capacity Expansion and New Energy Center

Project

Site restructuring including a feasibility study, planning, execution and commissioning of a new production facility.

Client

Mikron Switzerland AG

Key Data

Planung und Realisierung
IE Technology
Planungs- und Bauzeit
27 Monate
Nutzfläche (Erweiterung)
7.940 m²
Investitionsvolumen (Gebäude)
CHF 15.6 Mio.
Investitionsvolumen (Energiezentrale)
CHF 2.5 Mio.

Working Together for Project Success

Services provided by IE Group

Services provided by IE Group

  • Flexibly usable production space thanks to an innovative structural concept
  • Sustainably generated energy from the newly built energy centre
  • Future-ready site concept with expansion options
  • Maximum Efficiency in the Use of Available Space
  • Construction delivered without interruption thanks to optimal construction and operations planning
  • Reliable adherence to deadlines and cost targets
“The industrial know-how of IE Technology's planners and their understanding of our strategic objectives made a major contribution to the successful delivery of our expansion project. The collaboration was excellent.”
Felix Arrieta
Felix Arrieta
General Manager

Challenges & Solutions

Zusammenführung der Produktion von zwei Standorten an einem Standort

Durch eine intelligente Umstrukturierung des Hauptsitzes in Boudry bündelte IE Technology die gesamte Produktion an einem Standort. Ein neues Produktionsgebäude wurde in das bestehende Areal integriert, während die vorhandenen Gebäude umgenutzt wurden – und das innerhalb von 27 Monaten, von der Machbarkeitsstudie bis zur Übergabe.

Maximale Nutzungsflexibilität trotz begrenzter Platzverhältnisse

Die neue Produktionshalle umfasst 3.600 m² und kommt mit nur sieben tragenden Stützen aus – ein innovatives Tragwerkskonzept, das maximale Flexibilität schafft und die Fläche weitgehend stützenfrei hält. Produktion und Entwicklung sind unter einem Dach vereint, ohne die Betriebsabläufe zu beeinträchtigen. Das Gesamtkonzept des Standorts wurde zudem so ausgelegt, dass zukünftige Erweiterungen möglich sind.

Deutliche Senkung des Energieverbrauchs dank neuer Energiezentrale

IE Technology realisierte eine neue Energiezentrale mit Hightech-Wärmepumpen und einer 1.300m² grossen Photovoltaikanlage. 100 % der vor Ort erzeugten Energie wird direkt am Standort genutzt. Damit ist die neue Produktionsanlage nicht nur ein Vorzeigeprojekt in Sachen Effizienz, sondern auch ein sichtbares Zeichen für Nachhaltigkeit – mit spürbaren Einsparungen im laufenden Betrieb.

The Project in Detail

Mikron Switzerland AG is a leading provider of automation solutions for the pharmaceutical, medical, electrical and automotive industries. To make production — previously spread across two separate sites in Boudry — more efficient, the company decided to restructure the site and appointed IE Technology as General Planner.

Based on an IE Master Plan, the industrial construction specialists from Zurich developed a tailored restructuring concept, consolidated the entire production at the headquarters in Boudry and created a state-of-the-art factory complex. The new complex also integrates the development department, features a sustainable Energy concept And, above all, enabled a significant increase in efficiency.

The Challenge

Micron's production had previously been split between two sites in Boudry, several hundred metres apart. The resulting long internal transport routes significantly reduced productivity and led to high running costs. In addition, growing demand meant the existing setup was reaching its capacity limits. The goal was therefore to concentrate all production at a single location and make it more efficient at the same time.

Key Success Factors

By intelligently restructuring the headquarters in Boudry, IE Technology's experts succeeded in consolidating the entire production at one production site and noticeably improving both efficiency and energy consumption. To achieve this, the planners focused on optimising the building concepts: a new production building was integrated into the existing site, while the remaining existing buildings were repurposed.

Despite the limited space available, production and the development department were accommodated in a single building. The New Production Hall Spans 3,600 m² with only seven load-bearing columns, providing maximum flexibility. The final decisive step towards greater efficiency was the new energy centre delivered by IE Technology, featuring high-tech heat pumps and a 1.300 m² photovoltaic system.

The energy generated here is consumed 100% directly at the site and, alongside the cost savings achieved, makes the new production facility a flagship for sustainability.

Download

Deepen Your Knowledge

Find out more in our Insight Project.

Discover further details in our Project Insight.