Meiereigenossenschaft eG Viöl – Masterplan Including Hygiene and Energy Concept for a New Dairy

Meiereigenossenschaft eG Viöl is one of the last independent dairies in Schleswig‑Holstein. IE Food carried out the feasibility study and was responsible for the Planning and Execution of a new dairy, including a comprehensive hygiene and energy concept.

Delivering a Growth‑Oriented Dairy in Record Time

Project

Feasibility study, planning and execution of a new dairy production facility.

Client

Meiereigenossenschaft eG Viöl

Key Data

Planning & Execution
IE Food
Investment Volume
EUR 18.5 million
Construction and Planning Time
2 years
Building Area
4,600 m²
Site Area
33,000 m²
Completion
60 days ahead of schedule

Working Together for Project Success

Services provided by IE Group

  • General planning for a new dairy facility
  • Doubling: food production to 200 million liters per year
  • Drinking water quality across the entire site through four on‑site wells
  • Hygiene concept with two clearly separated and easy‑to‑clean hygiene zones
  • Energy concept including refrigeration systems, combined heat and power unit and on‑site biological wastewater treatment
  • Environmentally sound wastewater treatment via the in‑house bio‑sewage plant
“The experts at IE Food achieved this ambitious project 60 days ahead of schedule. That is an outstanding achievement.”
Ulrich Lembcke
Ulrich Lembcke
Managing Director Meiereigenossenschaft eG Viöl

Challenges & Solutions

Two‑Stage Hygiene Concept for Safe Dairy Processing

IE Food developed a structured hygiene concept with two clearly defined hygiene zones and corresponding airlock systems. This ensures product safety, simplifies cleaning processes and maintains a consistently high hygiene standard.

Self‑Sufficient Water Supply and Sustainable Energy Concept

IFour on‑site wells provide drinking‑water quality and make the dairy independent of public supply. The integrated energy concept addresses the specific requirements of milk processing and supports long‑term operational efficiency.

The Project in Detail

The objective of the project was to more than double milk processing capacity while creating reserves for future expansion. At the same time, production had to be transferred step by step from the existing facility to the new dairy without disrupting operations. Milk processing presents particular technical challenges due to its high energy demand, significant consumption of drinking water and large volumes of wastewater. Special solutions were therefore required, especially for the treatment of dairy wastewater and vapour condensate from the evaporation of skimmed milk, which cannot be discharged into the municipal wastewater system.

The success factors

Decisive for the selection of  IE Food  IE Food were its in‑depth expertise in milk processing, cross‑sector experience, strong market knowledge and a proven network of reliable partners. The result is a new dairy facility with a holistic hygiene and building concept. Product and personnel flows are now consistently separated, surfaces are easier to clean and hygiene standards are ensured at a permanently high level. Thanks to IE Group’s proven planning approach and integrated execution model, the new dairy was completed in record time. Processing capacity was increased to more than 200 million litres of milk per year, creating a robust foundation for long‑term growth.

Download

Deepen Your Knowledge

Discover further details in our Project Insight.