New construction of a seven‑storey facility including nitrogen garage, high‑performance test bench and workshop. Planning and execution as general contractor
Client
HW Bogen GmbH / SSR Performance GmbH
Key Data
Working Together for Project Success
Services provided by IE Group
- Concept and system planning
- High degree of automation
- General planneing
- Execution as General Contractor
- Close cooperation with Büro Bösel Hohberg Architects
Challenges & Solutions
Highly effective corrosion protection
A high‑performance test bench of exceptional scale
Technical Innovation without Existing References
Coordination of specialized partners
The Project in Detail
SSR Performance in Munich specializes in high‑end vehicles and motorsport. For a select group of collectors, the company operates a purpose‑built facility for the professional storage, maintenance and protection of classic and sports cars. IE Technology was responsible for the Planning and Execution of this specialized construction project as general planner and contractors.
The Challenge
SSR Performance set out to create a service offering unique in Europe: a nitrogen garage for classic cars combined with a high‑performance test bench for sports cars under one roof. The technical requirements exceeded those of conventional industrial buildings and demanded highly specialized solutions.
The Success Factors
1. Expert coordination and project management
Two primary technical requirements shaped the project: maximum corrosion protection with automated vehicle storage, and an extremely powerful test bench capable of four‑digit horsepower simulations. This required the coordinated involvement of specialists in oxygen reduction, robotics, ventilation, fire protection and related disciplines.
2. IE Technology as general planner and general contractor
IE Technology worked in close partnership with Büro Bösel Hohberg Architects to develop prototype solutions for both the nitrogen garage and the test bench. The result is a seven‑storey building with underground parking levels, a ground‑floor workshop and test bench, and upper floors housing technical systems, storage, showroom, office and conference areas.
3. Nitrogen atmosphere for corrosion and fire protection
The underground storage levels accommodate 141 vehicles. Nitrogen inertization reduces oxygen levels to approximately 7 percent. Humidity and temperature are continuously monitored, preventing corrosion and mold growth while providing effective fire protection. Vehicles are stored fully automatically using a flat‑robot system that only contacts the tires. Security systems compliant with VdS guidelines protect against theft.
4. A test bench of exceptional performance
The dynamometer measures outputs of up to 2,000 hp and speeds of up to 350 km/h. Two turbines supply up to 130,000 m³ of air per hour via the main airflow and up to 4,000 m³ via secondary jets. Air speeds of up to 200 km/h can be simulated, with intake temperature held constant at +20 °C regardless of external conditions.